An electrical rough-in inspection checks the wiring, boxes, cable, and panel before walls and ceilings are closed. Inspectors verify box fill, cable support and protection, receptacle spacing, circuit planning, and grounding while the wiring is still visible.
- Inspection must happen before insulation and drywall go up, because hidden wiring is costly to fix.
- Boxes must be sized for the number of wires they hold, since overfilling creates heat and fire risk.
- Cable must be stapled within the required distance of each box and protected where it passes through studs.
- No point along a habitable room's wall floor line may be more than 6 feet from a receptacle.
- Missing staples and unprotected cable through studs are the two most frequent rough-in defects.
Table of Contents
- What Electrical Rough-In Means and When It Happens in the Schedule
- Electrical Boxes, Cable, and Conduit: Placement and Fill Rules
- Outlet Spacing, Circuit Planning, and Minimum Room Requirements
- Electrical Wiring Installation in a House: Step-by-Step Sequence
- How to Rough-In an Electrical Panel
- Residential Electrical Rough-In Inspection Checklist
- How to Get Ready for a Rough-In Electrical Inspection
- Frequently Asked Questions
What Electrical Rough-In Means and When It Happens in the Schedule
Electrical rough-in is the stage where the wiring, boxes, and cable for a building are installed before the walls and ceilings are closed.
Rough-in happens after framing and before drywall, and it usually runs alongside plumbing and HVAC work. Walls stay open during this window, which is why the inspection must happen before insulation and drywall go up.
Common sequence on a new build:
- Framing is complete and the roof is on
- Plumbing and HVAC rough-in is underway
- Electrical rough-in is installed and labeled
Schedules vary by project, so confirm timing with your general contractor and local building department.
Electrical Boxes, Cable, and Conduit: Placement and Fill Rules
Electrical boxes hold the connections for outlets, switches, and fixtures. Each box must be sized for the number of wires it holds. Overfilling a box creates heat and a fire risk, so inspectors check box fill closely.
Cable must be secured within a set distance of each box and protected where it passes through studs or joists. A helpful starting point is the NFPA overview of the National Electrical Code.
Quick placement checks:
- Boxes are flush with the finished wall surface
- Cable is stapled within the required distance of each box
- Holes drilled through studs are located away from the stud edges
Outlet Spacing, Circuit Planning, and Minimum Room Requirements
Outlet spacing and circuit minimums are set by code, and the rules differ by room. The National Electrical Code (NEC) is the model most jurisdictions adopt, but the adopted edition and local amendments vary, so always confirm the requirements your local authority having jurisdiction (AHJ) enforces before you lay out boxes. A useful starting point is the NFPA overview of the National Electrical Code.
The 6-foot / 12-foot receptacle rule
In habitable rooms, code requires receptacle outlets so that no point along the floor line of any wall space is more than 6 feet from a receptacle. Wall spaces 2 feet or wider count, and the spacing is measured along the floor line, not diagonally. The practical effect is that receptacles are typically placed within 6 feet of each other and within 6 feet of any break in the wall, such as a doorway. This rule is what keeps extension cords from becoming permanent wiring.
Watch out: A common layout error is measuring from the center of a doorway or from the corner of a room rather than along the actual floor line of each wall space. That mistake can leave a 2-foot wall segment without a receptacle and fail inspection.
Room-by-room minimums to verify locally
Use this as a starting checklist, then confirm each line against the code edition your AHJ enforces.
- Kitchen: At least two 20-amp small-appliance branch circuits serving countertop receptacles. Countertop receptacles are GFCI-protected. Receptacles are required along countertop wall spaces so no point is more than 24 inches from a receptacle, and at least one receptacle is required on islands and peninsulas. Dedicated circuits are typical for the dishwasher, disposal, and any fixed appliance.
- Bathrooms: At least one 20-amp branch circuit serving bathroom receptacles, with GFCI protection at every receptacle. Receptacles are required within 3 feet of the outside edge of each basin.
- Bedrooms and living areas: AFCI protection is required on most 120-volt branch circuits in dwelling units under current editions. Receptacle spacing follows the 6-foot / 12-foot rule.
Circuit planning and load
Circuit planning starts with a load calculation, which determines the service size and the number of branch circuits. A 200-amp service is common for new homes with electric ranges, dryers, and HVAC, but the calculation, not habit, should drive the decision. Grouping loads sensibly (lighting separate from small appliances, dedicated circuits for large motors) reduces nuisance tripping and makes future additions easier.
Watch out: Sizing the panel only for today's loads is a frequent regret.
Recommended upgrades beyond code minimum
Code minimums are a floor, not a target. Many builders plan extra capacity during rough-in for an electric vehicle charger, a home workshop, a heat-pump water heater, or future battery storage.
The table below lists the room-by-room minimums the article gives, so you can check each one against your local code.
| Room | Requirement | Note |
|---|---|---|
| Kitchen | Two 20-amp small-appliance branch circuits | Countertop receptacles are GFCI-protected |
| Bathroom | One 20-amp branch circuit | GFCI at every receptacle |
| Bedrooms and living areas | AFCI on most 120-volt circuits | Follows the 6-foot / 12-foot rule |
| Laundry | Dedicated 20-amp circuit | GFCI where the code edition requires it |
| Garage | One 20-amp branch circuit | GFCI-protected receptacles |
| Basement | At least one receptacle | GFCI protection for unfinished areas |
| Outdoors | At least one receptacle front and back | GFCI-protected for a one-family dwelling |
| Hallway | At least one receptacle | Required in hallways 10 feet or longer |
Electrical Wiring Installation in a House: Step-by-Step Sequence
Residential wiring follows a logical order. Working in sequence keeps the job moving and makes inspection easier.

- Review the plans and load calculation. Confirm the panel size, the circuit count, and the location of every outlet, switch, and fixture.
- Mount the panel and service equipment. Install the main panel where the plan calls for it, with clear working space around it.
- Install boxes. Set boxes at the correct height and depth for each device.
- Run cable. Pull cable from the panel to each box, keeping runs neat, protected, and stapled.
- Make up connections in the boxes. Leave the right amount of free conductor at each box for the finish devices.
- Label circuits. Mark each cable at the panel and each box so the finished wiring is easy to trace.
- Schedule the rough-in inspection. Have the work reviewed before insulation and drywall are installed.
Following this sequence on site helps the crew avoid rework.
How to Rough-In an Electrical Panel
A panel rough-in is the mounting and wiring of the main service panel before the walls are closed. The work includes mounting the enclosure, running the feeder and branch cables into it, and leaving space for the breakers that will be added later.
Key steps for a panel rough-in:
- Confirm the panel rating matches the home's load calculation, such as a 200-amp service
- Mount the panel on a solid, accessible wall with the required clearances
- Route the service feeder and branch cables into the correct knockouts
A common mistake is sizing the panel only for today's needs.
Residential Electrical Rough-In Inspection Checklist
Use this checklist to review your own work before the inspector arrives. It is organized by what inspectors actually look at, with the common failure and the fix beside each item. Local requirements differ, so treat it as a starting point and confirm against the code edition your AHJ enforces.
Boxes and enclosure
- Boxes are the correct size for the conductors and devices they hold, and box fill is within the limits in the code's box-fill tables.
- Boxes are flush with the finished wall surface, or within the allowed setback for the surface type.
- Boxes are rigidly secured to framing and do not move when pushed.
Watch out: Overfilled boxes are one of the most common rough-in failures. The fix is to replace the box with a larger one or add an extension ring, not to cram the conductors.
Cable and conduit
- Cable is secured within the required distance of each box and at the required intervals along the run.
- Cable is protected by plates or sleeves where it passes through framing within the required distance of the stud or joist edge.
- Cable is not damaged, kinked, or stapled through the jacket.
Watch out: Missing staples and unprotected cable through studs are the two most frequent rough-in defects. A slow walkthrough before the inspector arrives can catch many of them.
Receptacles, switches, and spacing
- Receptacle spacing in habitable rooms meets the 6-foot / 12-foot rule along the floor line.
- Kitchen countertop receptacles meet the spacing and island/peninsula requirements.
- Bathroom receptacles are within the required distance of each basin.
Circuits and protection
- Dedicated circuits are installed for kitchen small appliances, laundry, bathrooms, and large fixed appliances.
- GFCI protection is planned for kitchens, bathrooms, laundry, garages, basements, and outdoors where the code edition requires it.
- AFCI protection is planned for the branch circuits the code edition requires.
Panel and service
- Panel location and working clearances match the plan and the code.
- Panel rating matches the load calculation.
- Service feeder and branch cables enter through the correct knockouts and are secured.
Documentation before drywall
- Photograph every wall bay, box, and panel with a tape measure or label visible.
- Record circuit numbers on the plans and store a copy on site and in the cloud.
- Note any deviations from the approved plans for the inspector.
Watch out: Pre-drywall photos are a useful record for the project. If a question arises later about a concealed run or a missing box, the photos resolve it without opening the wall.
How to Get Ready for a Rough-In Electrical Inspection
Preparation makes the inspection faster and reduces the chance of a failed inspection.
- Confirm the schedule. Book the inspection with the local building department once the rough-in is complete.
- Walk the job first. Go through the checklist above room by room.
- Clear access. Keep the panel, boxes, and walkways free of debris.
- Have documents ready. Keep the approved plans, permit, and load calculation on site.
- Fix problems before the visit. Correcting a loose staple or an overfilled box beats a re-inspection.
Most failed inspections come from simple items such as missing staples, unprotected cable, or boxes set at the wrong depth. A careful walkthrough catches most of them.
Planning new construction electrical work? S&T Electrical Solutions is a Washington Master Electrician-led contractor serving the Wenatchee Valley, and the team walks clients through the project scope from the first conversation to the final walkthrough. Request a quote from S&T Electrical Solutions to discuss rough-in planning for your next build.
Frequently Asked Questions
What is considered rough-in for electrical?
Electrical rough-in is the stage where boxes, cable, conduit, and the service or subpanel are installed and wired before drywall, insulation, and finish work. Devices such as outlets, switches, and fixtures are not yet installed. The work is inspected while walls and ceilings are still open so the inspector can see cable routing, box placement, support, protection, and grounding. Passing rough-in lets the rest of the project proceed under the local building permit.
What is required for a rough-in electrical inspection?
The inspector needs open access to all wiring: boxes securely fastened and set to the correct depth, cable supported and protected where it passes through studs or runs near edges, conductors sized and connected properly, and the panel or subpanel mounted with its circuits labeled. Grounding and bonding conductors must be in place. Any required fire stopping at wall penetrations should be done. Check the scope with your local authority having jurisdiction, since requirements vary by jurisdiction.
How do you prepare for an electrical rough-in inspection?
Walk the house before calling for the inspection. Confirm every box is fastened, flush to the framing, and accessible, and that cable is stapled within the distances your code requires. Remove debris and make sure the panel is accessible with clear working space. Take dated photos of wiring before insulation and drywall cover it, since these records help if questions come up later. Keep the approved permit and plans on site for the inspector.
What is the 2-6-12 rule for electrical outlets?
The 2-6-12 rule is a common guideline for receptacle spacing in living areas: no point on a wall should be more than 2 feet from a receptacle, and receptacles should be placed so that no wall space 2 feet or wider is left without one. Many modern codes use a similar but not identical rule, so confirm the exact spacing requirements in the electrical code adopted by your jurisdiction before laying out outlets.